Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
A101-2007: A101™–2007, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum Learn more $32.99: A101-2007 KDE: Kentucky Department of Education Version of AIA Document A101™–2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum Learn. EX-10.1 2 d315021dex101.htm AIA DOCUMENT A101-2007 STANDARD CONTRACT FOR CONSTRUCTION. AIA standard form. And 2007 by The American Institute of Architects. Aia contract documents are copyrighted by the american institute of architects. Samples of aia contract documents are provided pursuant to a special, non-transferable and limited license granted to bruce merwin, esq. By the american institute of architects on november 14, 2014.
Hi There Im looking for AIA's A101-2007 in a word format that I can re use. Anyone know where I should look? Free would be best. I've already spent a ton on these things. Some abbreviated reference thereof, shall mean AIA Document A101™-2007 Standard Form of Agreement Between Owner and Contractor, SCOSE edition. Any reference in this document to the General Conditions of the Contract for.
AGREEMENT made as of the Twelfth day of March in the year Two Thousand Twelve
(In words, indicate day, month and year)
BETWEEN the Owner:
(Name, legalstatus, address and other information)
Peerless Manufacturing Company
Suite 500
Telephone Number: 214-353-5545
Fax Number: 214-351-0194
And the Contractor:
(Name, legal status, address and other information)
2349 Glenda Lane
Dallas, Texas 75229
Telephone Number:972-243-7674
Fax Number: 972-243-7710
(Name, location and detailed description)
New Facility – Peerless Manufacturing Company
Denton, TX
(Name, legal status, address and other information)
Alliance Architects, Inc.
1600 N. Collins BlvdSuite 1000
Richardson, TX 75080
Telephone Number: 972-233-0400
Fax Number:972-233-2259
The Owner and Contractor agree as follows.
ADDITIONS AND DELETIONS:
This document has important legal consequences. Consultation with an attorney isencouraged with respect to its completion or modification.
AIA Document A201™–2007, General Conditions of the Contract forConstruction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified.
Init. / | AIA Document A101TM – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® |
User Notes: | (1517771384) |
1
TABLE OF ARTICLES
1 | THE CONTRACT DOCUMENTS |
2 | THE WORK OF THIS CONTRACT |
3 | DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION |
4 | CONTRACT SUM |
5 | PAYMENTS |
6 | DISPUTE RESOLUTION |
7 | TERMINATION OR SUSPENSION |
8 | MISCELLANEOUS PROVISIONS |
9 | ENUMERATION OF CONTRACT DOCUMENTS |
10 | INSURANCE AND BONDS |
ARTICLE 1 THE CONTRACT DOCUMENTS
The Contract Documents consist of this Agreement, Conditions of the Contract (General,Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement, all of which form the Contract,and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements,either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9.
ARTICLE 2 THE WORK OF THIS CONTRACT
The Contractor shall fully execute the Work described in the Contract Documents, exceptas specifically indicated in the Contract Documents to be the responsibility of others.
ARTICLE 3 DATE OFCOMMENCEMENT AND SUBSTANTIAL COMPLETION
§ 3.1 The date of commencement of the Work shall be the date of this Agreement unlessa different date is stated below or provision is made for the date to be fixed in a notice to proceed issued by the Owner.
(Insert the dateof commencement if it differs from the date of this Agreement or, if applicable, state that the date will be fixed in a notice to proceed.)
Ten (10) business days after receipt of all construction permits and fully executed Prime Contract.
If, prior to the commencement of the Work, the Owner requires time to file mortgages and other security interests, the Owner’s time requirementshall be as follows:
N/A
§ 3.2 The Contract Time shall be measured from the date of commencement.
(Insert number of calendar days. Alternatively, a calendar date may be used when coordinated with the date of commencement. If appropriate, insertrequirements for earlier Substantial Completion of certain portions of the Work.)
Init. / | AIA Document A101TM – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® |
User Notes: | (1517771384) |
2
Portion of Work | Substantial Completion Date |
, subject to adjustments of this Contract Time as provided in the Contract Documents.
(Insert provisions, if any, for liquidated damages relating to failure to achieve Substantial Completion on time or for bonus payments for earlycompletion of the Work.)
ARTICLE 4 | CONTRACT SUM |
§ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the Contract. The ContractSum shall be Nine Million Eight Hundred Thirty-nine Thousand Five Hundred Seventy-two Dollars and Zero Cents ($9,839,572.00), subject to additions and deductions as provided in the Contract Documents.
§ 4.2 The Contract Sum is based upon the following alternates, if any, which are described in the Contract Documents and are hereby acceptedby the Owner:
(State the numbers or other identification of accepted alternates. If the bidding or proposal documents permit the Owner toaccept other alternates subsequent to the execution of this Agreement, attach a schedule of such other alternates showing the amount for each and the date when that amount expires.)
§ 4.3 Unit prices, if any:
(Identify and state the unit price; state quantity limitations, if any, to which the unit price will be applicable.)
Item | Units and Limitations | Price Per Unit ($ 0.00) |
§4.4 Allowances included in the Contract Sum, if any:
(Identify allowance and state exclusions, if any, from the allowance price.)
Item | Price | |
Residential Appliances | $ | 10,000.00 |
Welding Gas System | $ | 70,000.00 |
ARTICLE 5 PAYMENTS
§ 5.1.1 Based upon Applications for Paymentsubmitted to the Architect by the Contractor and Certificates for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.
§ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or asfollows:
The 25
(Federal, state or local laws may require payment within a certain period of time.)
§ 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor in accordance with theContract Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Owner mayrequire. This schedule, unless objected to by the Owner, shall be used as a basis for reviewing the Contractor’s Applications for Payment.
Init. / | AIA Document A101TM – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® |
User Notes: | (1517771384) |
3
§ 5.1.5 Applications for Payment shall show the percentage of completion of each portion of theWork as of the end of the period covered by the Application for Payment.
§ 5.1.6 Subject to other provisions of the ContractDocuments, the amount of each progress payment shall be computed as follows:
.1 | Take that portion of the Contract Sum properly allocable to completed Work as determined by multiplying the percentage completion of each portion of the Work by theshare of the Contract Sum allocated to that portion of the Work in the schedule of values, less retainage of Ten percent (10%). Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute shall be included asprovided in Section 7.3.9 of AIA Document A201™–2007, General Conditions of the Contract for Construction; |
.2 | Add that portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in thecompleted construction (or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing), less retainage of Ten percent (10%); |
.3 | Subtract the aggregate of previous payments made by the Owner; and |
.4 | Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Section 9.5 of AIA Document A201–2007. |
§ 5.1.7 The progress payment amount determined in accordance with Section 5.1.6 shall be further modifiedunder the following circumstances:
.1 | Add, upon Substantial Completion of the Work, a sum sufficient to increase the total payments to the full amount of the Contract Sum, less such amounts as the Architectshall determine for incomplete Work, retainage applicable to such work and unsettled claims; and |
(Section9.8.5 of AIA Document A201–2007 requires release of applicable retainage upon Substantial Completion of Work with consent of surety, if any.)
.2 | Add, if final completion of the Work is thereafter materially delayed through no fault of the Contractor, any additional amounts payable in accordance withSection 9.10.3 of AIA Document A201–2007. |
§ 5.1.8 Reduction or limitation of retainage, if any, shall beas follows:
(If it is intended, prior to Substantial Completion of the entire Work, to reduce or limit the retainage resulting from thepercentages inserted in Sections 5.1.6.1 and 5.1.6.2 above, and this is not explained elsewhere in the Contract Documents, insert here provisions for such reduction or limitation.)
§ 5.2 FINAL PAYMENT
.1 | the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct Work as provided in Section 12.2.2 of AIA DocumentA201–2007, and to satisfy other requirements, if any, which extend beyond final payment; and |
.2 | A final Certificate for Payment has been issued by the Architect. |
ARTICLE 6 DISPUTE RESOLUTION
For any Claim subject to, but not resolved by,mediation pursuant to Section 15.3 of AIA Document A201–2007, the method of binding dispute resolution shall be as follows:
Init. / | AIA Document A101TM – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® |
User Notes: | (1517771384) |
4
(Check the appropriate box. If the Owner and Contractor do not select a method of binding disputeresolution below, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims will be resolved by litigation in a court of competent jurisdiction.)
[ X ] Arbitration pursuant to Section 15.4 of AIA Document A201–2007
[ ] Litigation in a court of competent jurisdiction
[ ] Other (Specify)
§ 7.1 TheContract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document A201–2007.
§ 7.2 TheWork may be suspended by the Owner as provided in Article 14 of AIA Document A201–2007.
ARTICLE 8 MISCELLANEOUS PROVISIONS
§ 8.1 Where reference is made in this Agreement to a provision of AIA Document A201–2007 oranother Contract Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract Documents.
§ 8.2 Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated below, or in the absencethereof, at the legal rate prevailing from time to time at the place where the Project is located.
(Insert rate of interest agreed upon, ifany.)
Eight percent (8%) Per Annum
With the app, visit a page written in a foreign language and Toolbar will automatically offer to translate it for you.Make your browser your ownGoogleToolbar gives you easy access to yours with bookmarks, custom buttons, and a display designed to feature only the tools you actually use.Note: For now, Google Toolbar is only available for Internet Explorer. Google toolbar download windows 8. Highlight search terms, find specific words, even jump to relevant sections of the page with three easy-to-use tools.Browse the whole webLanguage shouldn’t be a barrier to exploring the web.
(Name, address and other information)
Vincent Hanlon
14651 NorthDallas Parkway, Suite 500
Dallas, TX 75254
Fax Number: 214-351-0194
Email Address: vhanlon@peerlessmfg.com
§ 8.4 The Contractor’s representative:
Jim Corry
2349 Glenda Lane
Dallas, TX 75229
Phone 972-243-7674
Fax 972-243-7710
Email Address: jcorry@schwob.com
§ 8.5Neither the Owner’s nor the Contractor’s representative shall be changed without ten days written notice to the other party.
§ 8.6 Other provisions:
ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS
Init. / | AIA Document A101TM – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® |
User Notes: | (1517771384) |
5
§ 9.1.2 The General Conditions are AIA Document A201–2007, General Conditions of theContract for Construction.
§ 9.1.3 The Supplementary and other Conditions of the Contract:
Document | Title | Date | Pages |
Construction Proposal (Exhibit “A”) | Revised Construction Cost Proposal | March 8, 2012 | 4 |
§ 9.1.4 The Specifications:
Exhibit “B”
Section | Title | Date | Pages |
§ 9.1.5 TheDrawings:
(Either list the Drawings here or refer to an exhibit attached to this Agreement.)
Exhibit “C”
Number | Title | Date |
§ 9.1.6 TheAddenda, if any:
Number | Date | Pages |
SBC Addendum #1 (Exhibit “D”) | April 29, 2011 | 15 |
Portions of Addenda relating to bidding requirements are not part of the Contract Documents unless the biddingrequirements are also enumerated in this Article 9.
§ 9.1.7 Additional documents, if any, forming part of the Contract Documents:
.1 AIA Document E201™–2007, Digital Data Protocol Exhibit, if completed by the parties, orthe following:
N/A
(List here any additionaldocuments that are intended to form part of the Contract Documents. AIA Document A201–2007 provides that bidding requirements such as advertisement or invitation to bid, Instructions to Bidders, sample forms and the Contractor’s bid arenot part of the Contract Documents unless enumerated in this Agreement. They should be listed here only if intended to be part of the Contract Documents.)
ARTICLE 10 INSURANCE AND BONDS
The Contractor shall purchase and maintain insurance and provide bonds as set forth in Article 11 of AIA Document A201–2007.
(State bonding requirements, if any, and limits of liability for insurance required in Article 11 of AIA Document A201–2007.)
Type of insurance or bond | Limit of liability or bond amount ($ 0.00) |
Init. / | AIA Document A101TM – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® |
User Notes: | (1517771384) |
6
This Agreement entered into as of the day and year first written above.
OWNER(Signature) | CONTRACTOR(Signature) |
Andrew Erickson, Vice President, Schwob | |
Ron McCrummen, CFO | Corporation General Partner |
(Printed name and title) | (Printed name and title) |
Init. / | AIA Document A101TM – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 2007 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® |
User Notes: | (1517771384) |
7
2349 Glenda Lane |
Dallas, Texas 75229 |
972.243.7674 Phone |
972.243.7710 Fax |
972.692.0129 Alt. Fax |
www.schwob.com |
Items in italics have been revised
Mr. Peter Burlage
Peerless Manufacturing Company
14651 NorthDallas Parkway
Suite 500
Dallas,Texas 75254
RE: | NEW FACILITY – PEERLESS MANUFACTURING COMPANY |
SUBJECT: Revised Construction Cost Proposal
Dear Mr. Burlage:
We proposeto construct the new Peerless Manufacturing Company facility in Denton, Texas per the following scope and clarifications for the lump sum amount of Nine Million Eight Hundred Eleven Thousand Eight Hundred Eighty and 00/100 Dollars
($ 9,811,880.00).
This constructioncost proposal is based on local City and State code requirements, a Geotechnical Investigation by Reed Engineering Group (dated 02/18/11), and Design Documents and Specifications provided by Alliance Architects (dated 04/08/11). See the attachedIndex of Drawings for revision dates.
COST SUMMARY:
Construction Proposal (05-19-11) | $ | 9,499,512.00 |
Cost Escalations | $ | 118,441.00 |
Scope modifications by Owner | $ | 193,927.00 |
Revised Construction Proposal Amount | $ | 9,811,880.00 |
SCOPE MODIFICATIONS BY OWNER:
1. | Piping for welding gases - (ALLOWANCE) | $ | 70,000.00 |
2. | Overhead crane revisions | ||
a. Change cranes 1 and 4 from 2 each 20 ton cranes toa total of 4 each 10 ton cranes | $ | 51,540.00 | |
b. Cranes 2 and 5 to remain 40 ton each | no change | ||
c. Change cranes 3 and 6 from 2 each 20 ton cranes to a total of 3 each 10 toncranes | $ | 11,858.00 |
Mr. Peter Burlage
RE: | NEW FACILITY – PEERLESS MANUFACTURING COMPANY |
SUBJECT: | Revised Construction Cost Proposal |
Revised March 3, 2012
Page 2
SCOPE MODIFICATIONS BY OWNER (continued):
3. | Add water and sewer piping stub-up at the northwest corner of 136 Spot Welding at column grid J7 for future acid basin to be provided and installed by theOwner | $ | 2,000.00 |
4. | Increase Compressor Shed to 25’-0” x 15’-0” x 10’-0” | $ | 2,288.00 |
5. | Add electrical and piping for welding gases at 3 additional welding workspaces to be located between column grid B3 and D3 | $ | 14,825.00 |
6. | Foundation revisions for 500 ton press at room 146 | to be determined | |
7. | Design costs for the future Paint and Blast Booth Building | $ | 25,000.00 |
8. | Schwob overhead and fee on scope modifications | $ | 16,416.00 |
MAJOR COST ESCALATIONS:
When a particular USB device is connected to a virtual machine for the first time, the host detects it as a new device named VMware USB Device and installs the appropriate VMware driver.On Windows XP and Windows Server 2003 host systems, the operating system prompts you to run the Microsoft Windows Found New Hardware wizard. Select the default action to install the software automatically. Vmware usb device driver.
• Miscellaneous steel material | $ | 19,669.00 |
• Drywall | no change | |
• PEMB materials | $ | 31,810.00 |
• PEMB Insulation | <$ | 3,118.00> |
• Overhead cranes | $ | 25,333.00 |
• Overhead cranes (material sales taxes left out of original bid) | $ | 35,747.00 |
• Plumbing | $ | 10,000.00 |
• HVAC | no change | |
• Electrical | <$ | 1,000.00> |
• Schwob overhead and fee | no change |
CLARIFICATIONS:
1. | Owner and Contractor each agree that following the execution of the Construction Contract, no on-site construction or development work, other than such work requiredby separate instrument per the development agreement, may begin or occur on the Owner’s property until Contractor receives a written authorization from Owner to proceed with such work. Contractor agrees that Owner will not be liable for anyliens placed on the property or in connection with the construction of any structures on the property unless Owner has given its prior written authorization for such work. Notwithstanding the foregoing, Owner agrees that Contractor may place ordersfor materials related to the project and that Owner will be responsible for costs incurred by Contractor for such orders. |
2. | This proposal is based on reaching mutually acceptable contract terms. |
3. | We have included builder’s risk insurance. |
4. | We have included the building permit and plan review fees. |
5. | We have included the bond costs for the on-site public utility improvements. |
Mr. Peter Burlage
RE: | NEW FACILITY – PEERLESS MANUFACTURING COMPANY |
SUBJECT: | Revised Construction Cost Proposal |
Revised March 3, 2012
Page 3
6. | Due to a lack of ground water concerns, we have not included casing piers in our proposal. However, we may need to case all or some of the piers due to water injectingthe building pad. This will be handled on a per unit rate if required. |
7. | We have provided building pad preparation as follows: |
• | Excavate to 5’-0” below building sub grade to a distance 5’-0” outside the building perimeter (10’-0” at all entrances). |
• | Water injection stabilization to a depth of 20’-0” below excavated grade (5 passes included). Additional passes will be handled on a per unitrate if required. |
• | Moisture condition and re-compact excavated soils. |
• | Stabilize compacted soil with a mixture of 6% lime to a depth of 6” below grade. |
8. | We have included chain link fences as 6’-0” tall in lieu of 8’-0” tall where shown. |
9. | We have included vinyl privacy slats at the fence along the north and west sides of the gravel lay down yard. |
10. | We have included V-groove rolling ornamental gates in lieu of cantilever gates due to the width of the proposed openings. |
11. | We have included manually operated gates. |
12. | We have included liner panels in the manufacturing space to 10’-0” AFF with exposed vinyl-faced batt insulation above. |
13. | Specification 41 1213 does not identify the capacity required for the parts lift at the mezzanine. We have included an Auto-Quip VRC with the following specifications: |
• | Capacity: 6,000 lbs. |
• | Platform size: 8’-0” x 12’-0” |
• | Vertical rise: 15’-0” |
• | Load height: 10’-0” |
• | Upper and lower gates with safety interlocks |
14. | We have included the compressed air loop and drops. All air compressors, dryers, gas tanks, gas loops and gas drops shall be provided and installed by the owner. Wehave provided a $70,000 ALLOWANCE to be approved by the Owner under the “SCOPE MODIFICATIONS BY OWNER” heading above. |
15. | Per Vince Hanlon’s directions, we have eliminated all scope and costs associated with FOCR #155 (Conditioned Workspace). |
16. | We have made structural accommodations for the Owner provided and installed jib cranes. |
17. | This proposal is valid for a period of thirty (30) calendar days from the date first indicated above. However, due to the volatility of the steel and coppermarkets, Schwob Building Company reserves the right to review, withdraw, and/or amend this proposal after this time. |
18. | The Construction Schedule is an estimated 336 calendar days (approximately 48 weeks). This duration is based on a Commencement Date of 10 days after receipt of allapplicable permits from the local governing authorities and an executed Owner/Contractor Agreement, whichever is greater. |
Mr. Peter Burlage
RE: | NEW FACILITY – PEERLESS MANUFACTURING COMPANY |
SUBJECT: | Revised Construction Cost Proposal |
Revised March 3, 2012
Page 4
EXCLUSIONS:
1. | Design and preconstruction services (under separate contract). |
2. | Off-site road improvements and public sidewalks (under separate contract). |
3. | Off-site drainage and utility improvements (under separate contract). |
4. | Material testing laboratory services (by Owner). |
5. | Material escalation costs. |
6. | Payment and performance bond costs. |
7. | Costs for the Payment and Performance Bond on any accepted alternates or unit prices. |
8. | Water and sewer impact fee and water meter fee costs from the City of Denton. |
9. | Charges, fees, or assessments from the local utility providers. |
10. | Certifications or fees for compliance with the International Energy Conservation Code. |
11. | We assume any rock excavation can be easily performed with normal excavation equipment. |
12. | Costs associated with unforeseen subsurface conditions. |
13. | Concrete curb and gutter at the 5-acre gravel storage area. |
14. | Fireproofing of structural steel. |
15. | Epoxy grout at tile finishes. |
16. | Exterior signage (by Owner). |
17. | Jib cranes (by Owner). |
18. | Air compressors and dryers (by Owner). |
19. | Gas tanks, loops and drops (by Owner). |
20. | Security system (by Owner). |
21. | Phone and data cabling (by Owner). |
22. | Final connections to owner-provided manufacturing equipment. |
23. | Lightning protection system. |
Mr. Peter Burlage
RE: | NEW FACILITY – PEERLESS MANUFACTURING COMPANY |
SUBJECT: | Revised Construction Cost Proposal |
Revised March 3, 2012
Page 5
ALLOWANCES:
1. | Residential appliances | $ | 10,000.00 |
We look forward to working with you on this project. If I can be of further assistance, please contact me at972-243-7674.
Sincerely,
SchwobBuilding Company, Ltd.
Charles G. Rachuig CPE
Attachments | Index of Drawings Index ofSpecifications Alliance Architects Addendum #1 |
xc: E211027